Airport FBO on Firm Footing
23-11-2005
Ottawa
,
Ontario
,
November 23, 2005
- Pouring of the concrete footings for the FBO building foundation started today.
Its full speed ahead, said Bruce Baird owner of Baird Construction Ltd. Well finish pouring the concrete today and have it covered over well ahead the winter cut-off.
Delivery of the prefab metal components for the two-storey office building and the 6,000 sq. ft. hangar is expected in March with completion slated for May, 2006.
Upon completion in early 2006, the FBO will serve the general aviation community and high-profile executives, government, sports, and entertainment travelers.

Footer work during site preparation

Footer pour for Terminal and Hangar Building

Knee wall brings up elevation for the Terminal Hangar Building
Contact:
John E. Phillips
240 Michael Cowpland Dr. Suite 103
Kanata, Ontario K2M-1P6
Phone: 613-271-0587
|